New Palestine High School

New Palestine, Indiana

SCOPE OF WORK

Responded to a fire emergency in the English wing at New Palestine High School and temporary board up was completed quickly to confine damage.

  • Complete cleaning of all surfaces within the entire school: including textbooks and other teaching tools, inside and outside of all lockers, kitchen and all kitchen tools and equipment, gymnasium bleachers, theater and all seating, HVAC duct system and locker rooms, just to name a few specific areas.
  • In the English wing, a complete renovation of (1) room and entire hallway and the cleaning of the other classrooms within this area
  • Installed a new ceiling and grid system in the hallway
  • Installed a new HVAC system in the classroom
  • Completely painted the interior of the English wing
  • Installed a new floor coverings and furniture in the (1) damaged classroom
  • Cleaned all floor coverings in the rest of the hallway and classrooms

VALUE OF WORK

< $300,000

TIME FRAME

Project completed within 30 days of start