Commercial Construction

Concrete Repair

University of Indianapolis Concrete

Indianapolis, Indiana

SCOPE OF WORK

Pinned location for the placement of a new concrete sidewalk that led from the University apartments to the dorms

  • Located all underground lines / pipes
  • Removed grass and dirt in preparation of fill material
  • Placed crushed, compacted stone
  • Formed new curved sidewalk forms
  • Poured new concrete
  • Tooked joints and placed expansion
  • Sealed new concrete, stripped forms and backfilled

VALUE OF WORK

< $25,000

TIME FRAME

Project completed within 7 days of start