Multi-Family Construction

EXTERIOR REMODEL

WATERSIDE AT CASTLETON

Indianapolis, Indiana

Scope of Work

The complete exterior rehabilitation of 22 apartment buildings, 1 clubhouse, 1 fitness center, and 1 maintenance building. The project consisted of the following elements:

  • New windows and aluminum wrap
  • New Certainteed vinyl siding over 3/8″ foam insulation
  • Removal of wood “circular” accents on each balcony
  • Balcony repair and selective rebuilding
  • Installation of new vinyl railing systems
  • New roofs at several apartment building entries
  • Concrete sidewalk replacement
  • Rear patio concrete replacement
  • Street drain replacement
  • Complete painting of un-sided elements

Value of Work

< $1,000,000

Time Frame

Project completed within 120 days of start